As part of our on going growth we have recently invested in a new Nitrogen tank to support increased volumes of cryogenic deflashing.

This will see our daily deliveries of nitrogen reduced to once a month and it will also provide increased pressure which will improve efficiency.

The tank required planning permission and a new plinth and the whole project took 6 months to realize.

On the day all went to plan as the team from Ainscough Cranes removed the old tank and installed the new tank all within 4 hours and we were back freezing rubber components the next day with minimal disruption.

We now await delivery of our new Mewo Deflashing machine from our partners in Germany.